Time and Work in the CAT Exam is one of the important topics covered in the quant section. These topics measure the correlation between the amount of work done, the time taken to complete that amount of work done and the efficiency of an individual or group of individuals performing that work. Fundamentally, the concept is based on the important time and work formula where Work = Rate x Time. The rate is the efficiency of work or the amount of work a person can do in a given time.
Basic Concepts in CAT Time and Work
You can check the basic concepts behind time and work.
Time and Work Particulars | Details |
---|---|
Work |
|
Work Rate / Efficiency |
|
Time |
Time = Work / Efficiency |
Combined Work |
A + B Efficiency = 1 / 10 + 1 / 15 = 1 / 6
|
Work Equivalence | Work done is directly proportional to the time taken and efficiency. Work = Time x Efficiency |
Inverse Relation between Time and Work | If the work is fixed, time and efficiency are inversely proportional Time ∝ 1 / Efficiency |
Alternate Work (Work–Rest Pattern) |
|
Fraction of Work | If a person works for a certain number of days, the fraction of work completed is Fraction of work = Efficiency x Time worked |
Time and Work Formula
Check the important formulas of time and work.
Particulars | Formulas |
---|---|
Work - Time Relation |
|
If A can do a work in x days and B can do the same work in y days, then |
x + y
xy
|
Three Persons Work Formula |
ABC
|
If A, B, C can do a work in x, y, z days respectively, then |
Work done by A, B, C together in 1 day
|
Efficiency and Work | If A is k times as efficient as B, then
|
For queries reach us by filling the Common Application Form . You can also directly post your doubts in our QnA zone . To talk to our experts directly call us on our toll-free number 1800-572-9877.
Are you feeling lost and unsure about what career path to take after completing 12th standard?
Say goodbye to confusion and hello to a bright future!
FAQs
- Forgetting to take the LCM of time values properly.
- Mismanaging negative work (when a worker or pipe undoes work).
- Not carefully reading conditions like “A is twice as efficient as B.”
- Mixing up time taken with efficiency ratio.
Split the work into parts:
- Calculate the work done till a point.
- Deduct it from the total work.
- Assign the remaining work to the new group of workers and calculate.
Efficiency is the amount of work done in one day (or one hour).
If a person completes a work in N days, then their efficiency = 1 / N of work per day.
Was this article helpful?




Similar Articles
25+ Word List for CAT 2025 Vocabulary & Other MBA Entrance Exams
XAT 2026 Cutoff for IMT Ghaziabad: Expected Percentile for PGDM
Last 3 Years Topic-wise Quant Weightage in XAT
Top Institutes Accepting XAT Scores 2026: Check Complete List
How Many Questions to Attempt in XAT 2025 to Score 96 Percentile?
List of Top IIMs in India 2026: Check Rankings, Cutoff, Fees, Courses Offered, Placement